 Perbaikan Tiga Jalan di Pulo Gebang Capai 80 Persen

Roads Repair Process in Pulo Gebang Reaches 80 Percent

East Jakarta Bina Marga Sub-department repairs three roads on Jalan Pulau Andalas Raya, Jalan Jawa, and Jalan Jatayu of Pulo Gebang Urban Village, Cakung Sub-district. Process of this road repair work has reached 80 percent.

This repair is including sidewalk arrangement. Thus its budget is Rp 4.35 billion

East Jakarta Bina Marga Sub-department Head, Muhammad Sholeh explained, his side repairs Jalan Pulau Andalas Raya as long as 720 meters with width 8 meters.

"This repair is including sidewalk arrangement. Thus its budget is Rp 4.35 billion," he added when surveying the location on Monday (11/4).

Next Year, Bina Marga Department Plans to Build Three Flyovers

Then, his side also repairs Jalan Jawa with length 629 meters and width 12 meters, and Jalan Jatayu with length 640 meters and width 5 meters.

"Budget to repair Jalan Jawa is Rp 4.3 billion while Rp 2.3 billion for Jalan Jatayu," he mentioned.

He admitted, this road repair is done according to the applicable regulations.

In this repair, his side uses FS 45 concrete and started the project since September 2019.

"We target it to finish in this month. This project is also assisted directly by Security Team for Government and Regional Development (TP4D)," he asserted.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1709 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1481 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1335 personFolmer
  4. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1120 personDessy Suciati
  5. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye815 personDessy Suciati